Procedure For Building A Deck
- No permit required
- Does not need to meet side or rear yard setback requirements
- Requires a development permit
- Must conform to side yard setback requirements of the underlying zoning
- May be placed as close as ten feet to the rear property line
- Requires a building permit
- The fee is based on the valuation of the structure
- Must conform to side and rear yard setback requirements of the underlying
zoning
- Must go through construction plan review process
- All decks must be unroofed and unenclosed
- All decks, regardless of height, must meet front yard setback requirements
of the underlying zoning
- Active easements must remain accessible